Page 326 - Tech handbook 2019 rev 6 whyperlinks
P. 326

  Read/Review entire corresponding MSA agreement.
                                   Complete MSA costing analysis per the MSA annex and price per the
                                     parts margin in the LTSA cost calcs.
                                   Complete LTSA Billing Summary.
                                   Contract Manager to review for final approval, prior to upload for
                                     distribution.

               ____ Create Agreement in D365. Per procedure:

               Newly Signed MSA with Factory
                   -  Agreement is negotiated and fully executed by VP of Product Support.
                   -  Signed MSA and forwarded to Supply Chain Manager, Contract Manager &
                       Administrative Coordinator.
                   -  HITLIST

                       ____ Folder is created on SharePoint in Corresponding Branches site.

                       ____ Location: “NES & WES Product Support - NES [WES] Contracts\MSAs\MSA
                            NAME – INNIO Contract #”.
                       ____ Fully signed agreement is named: “! ! FINAL Signed MSA NAME– INNIO
                            Contract #”.
                       ____ Parts Tracker Reconciliation Summary Created. Per procedure:
                       ____ Parts Numbers created in ICS and D365 Per procedure:
                       ____ Add to MSA Invoicing Approval File



               Newly Signed MSA with Customer

                   -  Agreement is negotiated and fully executed by VP of Product Support.
                   -  Signed MSA and forwarded to Supply Chain Manager, Contract Manager &
                       Administrative Coordinator.
                   -  HITLIST

                       ____ Folder is created on SharePoint in Corresponding Branches site.

                       ____ Location: “NES & WES Product Support - NES [WES] Contracts\MSA
                            Onlys\MSA NAME”.
                       ____ Fully signed agreement is named: “! ! FINAL Signed MSA NAME 091616”.
                       ____ Cost calculation files filed here as well.

                       ____ Determine whether the assets are running, if not acquire projected commissioning
                            date from Product Support or Engineering.

                       ____ Notify branch and initiate invoicing with Product Support Administrator.