Page 67 - Tech handbook 2019 rev 6 whyperlinks
P. 67

1a:




























                       Before each rail is installed they are to be marked for location.  Each rail being measured
                       at position above and marked down in the WES/NES data capture sheet.

                       Illustration 1c shows proper technic for measuring at each rail correct designation.  If rail
                       exceeds +/- 3mm from 0-hour measurement, please contact management.   A and B 1
                       rails are very short in length and one only one measurement in center is required.
                       Rubber rails 2 and 3 require a measurement one inch from each edge (measurements 1
                       and 3), measurement 2 should be centered.

                              *** Note most important in the measurement process is consistency in both
                       technic used for measuring and position measurements are taken