Page 67 - Tech handbook 2019 rev 6 whyperlinks
P. 67
1a:
Before each rail is installed they are to be marked for location. Each rail being measured
at position above and marked down in the WES/NES data capture sheet.
Illustration 1c shows proper technic for measuring at each rail correct designation. If rail
exceeds +/- 3mm from 0-hour measurement, please contact management. A and B 1
rails are very short in length and one only one measurement in center is required.
Rubber rails 2 and 3 require a measurement one inch from each edge (measurements 1
and 3), measurement 2 should be centered.
*** Note most important in the measurement process is consistency in both
technic used for measuring and position measurements are taken
3 | P a ge