The new Freshman Academy is designed to create a school-within-a-school easing the transition
               of students into the high school environment. An addition is located at the south side of the existing
               school and some additional space is renovated within the east end of the existing south wing. The
               Freshman  Academy  addition with  the  renovation  of  the  administrative wing  of  the  school  will
               create a new front door and Welcome Center for Morton West. This along with a new drive and
               visitors  parking  area  will  clarify  where  visitors  enter  the  building  and  place  those  services  that
               parents  need  to  access  in  proximity  to  the  front  door  and  Welcome  Center.  Student  Support
               Services are located at the north end of the administrative wing in proximity to the Cafeteria. A
               separate Freshman Academy administrative function is also directly accessed from the new front
               entry and Welcome Center.

               The Freshman Academy will accommodate eight teams of students and teachers with three
               classrooms and a science prep lab per team and two teams sharing a STEM Lab. The Freshman
               Academy  is  created through  a  combination  of  an addition  and  renovation  of  space  in the
               eastern portion of the existing south wing. Eight teams are grouped around a Great Room with
               a  major  stair/amphitheater  serving  as  an  assembly  space  and  collaborative  learning
               environment. Flex Classrooms for specialties are arranged below a second floor satellite cafeteria
               and  at  the  top  of  the  amphitheater.  Each  team  also  has  breakout  space  within  a  widened
               corridor for collaborative and project based learning activities.

               A third component of the project, will convert the existing Library into a student centered multi-
               media collaboration and production center or Knowledge Commons. This will expand the library
               to  encompass  the  entire  second  floor  of  an  existing  academic  wing  and  create  spaces  that
               support collaborative and project based learning – breakout areas, small group meeting rooms,
               maker space, “genius bar”, and 35,000 volumes.

               The project is scheduled for completion in August 2019.