5.3 SAFETY REQUIREMENTS

                      The following safety requirements shall be strictly followed at the biomining site:-
                      No unauthorized entry of men, material and vehicles

                      Adequate provisions for controlling flies
                      No smoking zone

                      Use of personal protective equipments shall be mandatory
                      The site or processing may cover with GI sheets to avoid the view of processing to
                       the residents. This cover can be removed once the site gets clear.
                5.4  PROJECT TIMELINE
                      The capacity of the machineries installed shall be capable of processing 400 TPH of
                      legacy  waste.  Considering,  work  to  be  in  shift  of  eight  hours  per  day,  total  legacy
                      waste  processed  per  day  shall  be  1600  TPD.  The  quantity  of  legacy  waste  in
                      Rishikesh is 271919 cu.m. Considering the density of waste to be 1 tonne per cu.m,
                      the total weight of waste is 27919 tonnes. The total time required for biomining should
                      be 167 days i.e. approximately 5-6 months. The time required for biomining can be
                      reduced by increasing the capacity of the processing machinery.