RISHIKESH NAGAR NIGAM
Dist- Dehradun State - Uttarakhand
Land Reclamation of Existing Municipal Solid Waste
Dumping Ground at Rishikesh, Uttarakhand
Proposed Rate For Biomining of Laegacy Waste
RATE ANALYSIS
Rs. per
d)Bioming machinery with Eectricity cum 100 100
Rs. per
E) Truck for disposal of inert cum 30 30
Rs. per
Total For Machinery (B) cum 434
Total For labour + Machinery
(A+B) 456.32
Add for Foul Condition @ 20% of
(A+B) 20% C 91.264
Total D 547.584
labour
amenitie
For labour & Machinery s 1% E 5.48
labour Welfare (For labour part only
) 1% F 0.22
Insurance 1% G 4.56
EPF 12.5% H 2.79
Total of E+F+G+H+I J 13.05
Overhead Charges 10% K 54.76
Total of D +J+K L 615.39
Contractors profit on total (L) 10% 61.54
Contigencies on total (L) 3% 18.46
Rs. per
Total Cost per Cum cum 695.40
Rs. per
Say cum 696.00