RISHIKESH NAGAR NIGAM
                                     Dist- Dehradun                     State - Uttarakhand
                                 Land Reclamation of Existing Municipal Solid Waste
                                     Dumping Ground at Rishikesh, Uttarakhand
                                    Proposed Rate For Biomining  of Laegacy Waste
                                                   RATE  ANALYSIS
                                                                           Rs. per
                         d)Bioming machinery with Eectricity               cum            100        100
                                                                           Rs. per
                         E) Truck for disposal of inert                    cum             30          30
                                                                           Rs. per
                         Total For Machinery                   (B)         cum                       434

                         Total For  labour + Machinery
                         (A+B)                                                                    456.32
                         Add for Foul Condition @ 20% of
                         (A+B)                                                   20%      C       91.264
                                                               Total                      D      547.584
                                                               labour
                                                               amenitie
                         For labour & Machinery                s                  1%      E          5.48
                         labour Welfare   (For labour part only
                         )                                                        1%      F          0.22
                         Insurance                                                1%      G          4.56
                         EPF                                                   12.5%      H          2.79
                         Total of  E+F+G+H+I                                              J         13.05
                         Overhead Charges                                        10%      K         54.76
                         Total of D +J+K                                                  L       615.39

                         Contractors profit on total (L)                         10%                61.54
                         Contigencies on total (L)                                3%                18.46

                                                                           Rs. per
                         Total Cost per Cum                                cum                    695.40
                                                                           Rs. per
                         Say                                               cum                    696.00






















                                                                                                        49