Page 45 - DPR Rishikesh Legacy_Neat
P. 45

Developer/Contractor  for  smooth  operation  of  the  machinery  and  equipment
                      installed by them.

                      Arrangement of Water, Sewage and Electricity required for the project will be the
                      responsibility of the Corporation. However, the cost of consumption shall be paid
                      by the Contractor as per actual usage based on appropriate meter readings from
                      the meters installed.


                 5.1.4 BIOMINING ACTIVITIES AND OPERATION

                    Excavation  of  the  existing  mixed  compacted  garbage  which  underwent  biological
                    degradation  in  the  land  portion  allocated/  earmarked  in  the  planning  stage.  An
                             1
                    excavator  of power 70 to 90 HP with bucket capacity of 1 to 1.5 cum may be used
                    for  excavation  work.  The  number  of  excavators  shall  depend  upon  the  volume  of
                    waste, capacity of the processing machinery and timeline of the work.

                    The excavator shall either transfer the waste in the dumper truck or place the waste in
                    the form  of  stock  piles. If  the  processing  machinery  is  located  distantly,  transfer of
                    waste has to be done using dumper truck. A dumper truck of 4 to 6 cu.m capacity
                    shall be used for waste transfer. The dumper truck shall unload the waste closer to
                    the  processing machinery.  A front  end  loader  shall  be  used  to feed  the  waste  into
                    hopper for further processing. The power of front end loader may be in the range 70
                    to 90 HP.
                    A setup involving a conveyor and a trommel for segregating the excavated material into
                    oversized,  under  sized  and  intermediate  portion  is  the  key  step  in  any  biomining
                    operation.  The  undersized  fine  fraction  generally  consists  of  decomposed  organic
                    matter, soil and humus etc., oversized matter is composed of metals, textiles, rubber
                    and plastics, intermediate sized fraction is made up of combustible materials, recyclable
                    materials  and  decomposed  organic  matter  upto  some  extent.  Ferrous  metals  are
                    generally taken off the stream by deploying a magnetic separator and an air classifier
                    arrangement is put in place to separate the non-ferrous metallic portion, leaving behind
                    combustible fraction from the waste.

                    The  size  and  type  of  screen  depend  on  the  end  use  of  the  recovered  material.  The
                    efficiency of the material recovery is largely governed by the waste composition, mining
                    technology and the efficiency of the segregation technology.
                      1.  The screening process is explained in the following points:-The excavated waste
                          shall be dumped in the hopper using the front end loader.

                      2.  The waste from hopper is fed onto a slow-moving (5 m per minute) conveyor belt.
                          Items  not  suitable  for  the  trommel,  such  as  glass  bottle,  metal  container,  any
                          hazardous material like containers of paint, etc. are taken out by hand and put in
                          appropriate bins. The workers should be provided with gloves to avoid injury. The
                          thickness of the moving waste pile on the conveyor belt should be less than 15
                          cm  (for  better  manual  sorting)  and  the  removed  material  stored  in  segregated




                                                                                                        45