Page 50 - DPR Rishikesh Legacy_Neat
P. 50

Rate analysis for the various components considered in the legacy waste biomining is presented in below Table 5-5.

                                                              Table 5- 5: Rate Analysis of Biomining machineries
                                                          units      processing/     Total                                           Per day
                Description                     cum/hr    required   per day         quantity  days    months  Rate      Unit        cost      Cost/cum
               Hydraulic Excavator for legacy
               waste Excavation and loading
               in truck                              25           8           1600    271919     167       5.66   7000  per day       56000            35
               Hydraulic Excavator for
               loading of legacy waste into
               Trommel                               25           8           1600    271919     167       5.66   7000  per day       56000            35
               Processing capacity of Sieve
               or Screening Trommel                  50           4           1600    271919     167       5.66    100  per cum      160000           100

               Internal Transport by Truck (5
               cum capacity for 200 m
               distance per trip) Total 5
               trips/hour                            25           8           1600    271919     167       5.66      3  cum/km        38400            24
               Transport to disposal site (10
               cum capacity for 15 Km
               distance per trip) Total 1
               Trip/Hour                             10           4            320  54383.8      167       5.66      5  cum/km        48000         150.0


                      For operation of 1600 TPD processing plant Manpower required and there per cost per cum is represented in below Table 5-6.

                                                     Table 5- 6: Rate Analysis of manpower required for Biomining process

                                                                            processing/
                                                            Person/Shift    transportation per day       Rate/day      Per day cost      Cost/Cum
                 Supervisor                                             4                      1600              738              2952          1.85
               Technician                                               4                      1600              775              3100          1.94
               Labour                                                  64                      1600              558            35712          22.32


                                                                                                                                                         50
   45   46   47   48   49   50   51   52   53   54   55