Rate analysis for the various components considered in the legacy waste biomining is presented in below Table 5-5.
Table 5- 5: Rate Analysis of Biomining machineries
units processing/ Total Per day
Description cum/hr required per day quantity days months Rate Unit cost Cost/cum
Hydraulic Excavator for legacy
waste Excavation and loading
in truck 25 8 1600 271919 167 5.66 7000 per day 56000 35
Hydraulic Excavator for
loading of legacy waste into
Trommel 25 8 1600 271919 167 5.66 7000 per day 56000 35
Processing capacity of Sieve
or Screening Trommel 50 4 1600 271919 167 5.66 100 per cum 160000 100
Internal Transport by Truck (5
cum capacity for 200 m
distance per trip) Total 5
trips/hour 25 8 1600 271919 167 5.66 3 cum/km 38400 24
Transport to disposal site (10
cum capacity for 15 Km
distance per trip) Total 1
Trip/Hour 10 4 320 54383.8 167 5.66 5 cum/km 48000 150.0
For operation of 1600 TPD processing plant Manpower required and there per cost per cum is represented in below Table 5-6.
Table 5- 6: Rate Analysis of manpower required for Biomining process
processing/
Person/Shift transportation per day Rate/day Per day cost Cost/Cum
Supervisor 4 1600 738 2952 1.85
Technician 4 1600 775 3100 1.94
Labour 64 1600 558 35712 22.32