Table 5- 1 Machineries and Timeframe required for Biomining activity
units Processing total
Description cum/hr required / per day quantity days months
Hydraulic Excavator for
legacy waste Excavation
and loading in truck 25 8 1600 271919 167 5.66
Hydraulic Excavator for
loading of legacy waste into
Trommel 25 8 1600 271919 167 5.66
Processing capacity of
Sieve or Screening
Trommel 50 4 1600 271919 167 5.66
Internal Transport by Truck
(5 cum capacity for 200 m
distance per trip) Total 5
trips per hr 25 8 1600 271919 167 5.66
Transport to disposal site
(10 cum capacity for 15 Km
distance per trip) Total 1 54383.
trips per hr 10 4 320 8 167 5.66
Table 5- 2 Manpower required for Biomining activity
For operation of 1600 TPD processing plant Manpower Person/ Processing/
required Shift day
Supervisor 4 1600
Technician 4 1600
Labour 64 1600
The segregated materials should be stored separately, and then to be sold off to
vendors. The rejects from the biomining activity which is not useful for any activity
should be dumped into the sanitary landfill at proposed MSW processing and disposal
site at Lal Pani.
5.2 COST ESTIMATES
As per strategy discussed in above chapters the cost estimates of various
components are presented in this chapter.
The costing for biomining depends on following factors:-
1. Quantity of the waste
2. Capacity of processing machinery
3. Area and location of scientific landfill
4. Manpower employed