Table 5- 1 Machineries and Timeframe required for Biomining activity

                                                       units      Processing    total
                Description                  cum/hr    required   / per day     quantity  days  months

               Hydraulic Excavator for
               legacy waste Excavation
               and loading in truck               25           8         1600  271919      167       5.66
               Hydraulic Excavator for
               loading of legacy waste into
               Trommel                            25           8         1600  271919      167       5.66
               Processing capacity of
               Sieve or Screening
               Trommel                            50           4         1600  271919      167       5.66

               Internal Transport by Truck
               (5 cum capacity for 200 m
               distance per trip) Total 5
               trips per hr                       25           8         1600  271919      167       5.66
               Transport to disposal site
               (10 cum capacity for 15 Km
               distance per trip) Total 1                                        54383.
               trips per hr                       10           4          320          8   167       5.66

                                     Table 5- 2 Manpower required for Biomining activity

               For operation of 1600 TPD processing plant Manpower           Person/       Processing/
               required                                                      Shift         day
               Supervisor                                                              4             1600
               Technician                                                              4             1600
               Labour                                                                 64             1600

                    The  segregated  materials  should  be  stored  separately,  and  then  to  be  sold  off  to
                    vendors. The rejects from the  biomining  activity  which  is  not  useful for any  activity
                    should be dumped into the sanitary landfill at proposed MSW processing and disposal
                    site at Lal Pani.


               5.2 COST ESTIMATES

                      As  per  strategy  discussed  in  above  chapters  the  cost  estimates  of  various
                      components are presented in this chapter.

                      The costing for biomining depends on following factors:-
                         1.  Quantity of the waste
                         2.  Capacity of processing machinery

                         3.  Area and location of scientific landfill
                         4.  Manpower employed