Step 3 - Evaluate the Risks and Decide on Precautions


               The term risk can be defined as ‘the likelihood of harm’. This is usually regarded to have two
               components:


               • The likelihood of the hazardous event occurring
               • The severity of the harm that results


               Thus, a better definition might be ‘the likelihood of harm together with the potential severity of
               harm that results from a hazard’.


               The simplest way to evaluate the risk is to allocate descriptions such as high, medium and
               Low to the level of risk. Another method is to use a numerical system, allocating numbers to
               variations in likelihood and severity, and then applying these to a matrix e.g.


               When  considering  the  severity  of  the  injury  that  may  result,  it  is  important  to  be  realistic.  If
               someone tripped over a trailing cable on the floor in a warehouse, the person may end up with
               bruises or a fractured bone. However, if the cable was running across the entrance to the busy
               metal stairs on the second floor, a more severe injury, even death may result. It is often useful to
               ask the question: ‘Based on actual injuries – how many of the injuries resulting from that hazard
               did result in the severity of injury that I have proposed?’


               Again, some organisations will adapt their own accident experience over these subjective
               statements with a view to making them more relevant for their own organisation. This simple
               model allows this, and customisation, without over complication, is to be encouraged.


               Risk rating


               In our simple risk assessment, the next stage is to multiply the ‘likelihood’ number by the
               ‘severity’ number to arrive at a risk rating for each hazard. The result of this exercise will
               provide a risk rating from 1 to 25, as seen in the table that follows.






















                                                     5×5 Risk assessment matrix