Page 36 - VYSNOVA PROGRAM MANAGEMENT GUIDE 20200625
P. 36

Subcontractor Management



                   Invoices and Payment Terms

                   •  The  PM shall require all  subcontractors and consultants to  submit invoices, along  with
                                                                           th
                       applicable monthly status reports and timesheets by the 5  business day of the subsequent
                       month.
                   •  The PM shall require all subcontractors be paid Net ten (10) business days after receipt of
                       payment from the client.
                   •  The PM shall require all consultants be paid Net ten (10) business days after receipt of an
                       approved invoice, provided the invoice is received in proper order.
                   •  The PM shall ensure all ACH Forms, Wire Forms, W-9 and or W-8 Forms  of the subcontractor
                       or consultant are completed by the subcontractor and returned to the CA no later than fifteen
                       (15) days after execution of the Agreement.

                   Subcontractor Travel and ODCs

                   •  PM shall reiterate and enforce that, unless otherwise negotiated by Vysnova Management, all
                       subcontractor travel shall be conducted, booked, and managed only through Vysnova when
                       Vysnova is the Prime.
                   •  When processing  travel reimbursements for OCONUS-based subcontractors,  the PM shall
                       adhere to local in-country rules, regulations, and industry practices.
                   •  When processing travel reimbursements for CONUS-based subcontractors, the PM shall
                       review and approve subcontractor invoices for reimbursement for actual costs incurred for
                       such expenses that are:
                       o  explicitly authorized and funded in written contract agreement
                       o  In compliance with the Federal Travel Regulations (FTR)
                       o  reasonable, allocable, and allowable costs in accordance with FAR Part 31 cost principles
                          and FAR 52.216-07
                       o  supported by adequate original documentation, such as Subcontractor's expense report
                          vouchers with receipts or other substantiating documentation.

                   Subcontractor Kick-Off
                   1.  The CA will facilitate the subcontractor kick-off with programmatic input from the PM.
                   2.  1-2 days prior to the subcontractor kick-off, the CA will forward the contract kick-off slide deck
                       to the PM.
                   3.  The PM shall provide project input for inclusion in the subcontractor kick-off slide deck. Input
                       shall include but is not limited to the following:
                       o  Scope Limits: describe the anticipated work of subcontractor(s)
                       o  Anything done outside the scope of the subcontract will not be reimbursed
                       o  Lines  of Communication: Required  communication intervals  (need-to-know, weekly,
                          monthly)
                       o  Identify points of contact for each subcontractor
                       o  Reporting  requirements:  Status report schedules,  monthly status reports,  meeting
                          schedules
                   •  The PM shall return the slides to the CA NLT 1 business day prior to the contract kick-off
                       meeting.




                                     Copyright 2020 Vysnova Partners Inc.  All rights reserved.


                   32
   31   32   33   34   35   36   37   38   39   40   41