Module 6: Budgeting

                                                                Solution to Module 6. REQUIREMENT

                                                                  2. Direct Costs are related to completing work that are


                                                                     directly  attributable  to  its  performance  and  are
                                                                     necessary  for  its  completion.  It  includes  the

                                                                     supervision  directly  involved  in  the  physical
                                                                     construction.


                                                                3. Indirect Costs are not directly attributable to the
                                                                     completion  of  an  activity,  typically  allocated

                                                                     across all activities on a predetermined basis.


                                                                4. From an owner’s perspective, the goal of the budget
                                                                     process  is  to  develop  a  budget  that  reflects  all
                                                                     anticipated costs of the project.



                                                                5. The  Two  major  components  that  forms  the  basis  of
                                                                     project controls are  Budget and Schedule.