Quantity Surveying: Guideline for Quantity Surveyor Chapter 6
Figure 6.6: Characteristics of Letter of Acceptance
Once successful contractor receiving the letter of acceptance, then contract
agreement bond relationship. Before contractor start work,contractor should be prepare:
Letter of acceptance need to be signed and am being returned to client
Submitt the SOCSO guarantee
Policies insurance
Receipt for premium payment for insurance policies
Without above matter contractor will not be allowed start a work. Performance
Bond is necessary to ensure that the contract will finish contract so, then this
implementation guarantee will be seized. Performance Bond could be made whether in
form of assurance bank or insurance guarantee.