Page 212 - BASIC GUIDELINE FOR QS
P. 212

Quantity Surveying: Guideline for Quantity Surveyor                                                         Chapter 6




                   1.     Acceptance of the client

                          Declare the agreement of the employer to accept the offer of the tenderer (tender
                          price and time of completion)


                   2.     As a binding contract
                          As  a  legal  binding  contract  before  the  formal  contract  agreement  is  made
                          (contract document)


                   3.     Empower the SO to make a price adjustment

                          To  authorize  the  Superintending  Officer  to  make  price  adjustment  (without
                          prejudice to the contract sum)


                   4.     Inform the successful contractor
                          Inform  the  successful  contractor  on  the  direction  to  be  followed  and  prepared
                          before being allowed to start work on site


                   5.     Stated the date of possession
                          Stated date of possession , the date the contractor can begin work on site