Quantity Surveying: Guideline for Quantity Surveyor Chapter 6
6.10 Contractor Failure Factors in Tender Participations
The following are factors contractor failure in tender participation:
Too high tender price.
The bid price is too low. If the work is also provided, it may result in loss or
the work may not be performed properly. The government will not be bound
to accept the lowest bid or any offer.
The hands-on work done at the time was too much and exceeded the
financial limit of registration.
The record of past works is poor and unsatisfactory.
Not comply any tender condition
The tender details are not filled correctly
Insufficient financial allocation for a single project.