Page 216 - Project+
P. 216

3       Budget              0.8               0.1         0.08      Y               Whatley        H Drive

             overrun

     4       Technical           0.5               0.5         0.25      N               White          IT Dept
             issues

     The risk owner is responsible for monitoring the risks assigned to them and watching

     for risk triggers. Risk triggers are a sign or a precursor signaling that a risk event is
     about to occur. If the risk requires a response plan, the owner should be prepared to
     put the response plan into action once a trigger has surfaced.


     Risk Monitoring

     You will need to monitor risks throughout the Executing and Monitoring and
     Controlling phases of the project.






                   Risk events have a higher probability of occurring and more impact early
       on in the project, while probability and impact decrease as you get closer to closing
       out the project.



     Use the risk register to communicate the project risks and action plans to the
     stakeholders. Include a risk update in your project status meetings, and periodically set
     up a risk review meeting to go through each risk on the risk register and determine
     whether they have occurred or are likely to occur. Risk typically diminishes over time,
     so risk rankings should change as well to reflect the current state of the project. New

     risks can come to light as you proceed with the work of the project, so be certain to
     make risk review a standard part of your project management process.

     If you’re working on a large project or one with an extended time frame, it’s good
     practice to reevaluate risks periodically. This involves starting again at the risk
     identification process, working through the probability and impact exercise and
     writing response plans for newly identified risks, and updating responses for existing
     risks.







       Main Street Office Move

       Kate is anxiously awaiting the estimated cost for the project. Now that the
       schedule is complete and you have resources assigned, you begin the process of
       estimating the costs of the tasks, including contract resources, supplies, and

       materials. The work packages are a great place to start. Your estimates are here:

        Description                   Work                      Rate/Each Estimated Comments

                                      Effort/Quantity                            Cost


                                                            216
   211   212   213   214   215   216   217   218   219   220   221