Page 218 - Project+
P. 218

Once you get new estimates, you’ll revise the budget and then present it to Kate

       and stakeholders. Once Kate approves and signs off on the budget, this becomes
       the official cost baseline for the project. You will monitor burn rate, expenditures,
       and report expenditures and the state of the budget to the stakeholders throughout
       the remainder of the project.

       You set up a meeting with the key stakeholders to determine the list of risks, their
       probability and impact, response plans, and risk owners, and you record this
       information in the risk register. Your sample risk register is shown here:


        Risk Description                      Prob Impact Risk                 Response Risk Owner
        #                                                          Score       Plan

        1       Moving company                .25      1           .25         Y                Procurement
                availability                                                                    manager

        2       Bad weather during            .25      .25         .0625       N                Project
                move                                                                            manager

        3       Furniture order               .10      1           .10         Y                Facilities
                delayed                                                                         manager





     Summary


     Cost estimating is performed after the schedule is created and the resources for the
     project have been determined. You can use several techniques to create project

     estimates. Analogous or top-down estimates use expert judgment and historical data to
     provide a high-level estimate for the entire project, a phase of the project, or a
     deliverable. Parametric estimating uses a mathematical model to create the estimates
     and, in its simplest form, multiplies the duration of the project task by the resource
     rate to determine an estimate. The bottom-up method creates the project estimate by
     adding up the individual estimates from each work package. Three-point estimates are

     the average of the most likely, optimistic, and pessimistic estimates.

     Cost estimates are used to make up the project budget. The project budget is
     established by using the organization’s chart of accounts and then documenting work
     effort, duration, equipment and material costs, and any other costs that may be
     incurred during the course of the project. The cost baseline is the total approved
     expected cost for the project and is used for forecasting and tracking expenditures

     throughout the project.
     Risk planning involves identifying potential risk events that could occur during the

     project, determining their probability of occurrence, and determining their impact on
     the project. Probability is always expressed as a number between 0.0 and 1.0. Risk
     response plans should be developed for those risks that have a high probability of
     occurrence, have a significant impact on the project if they occur, or have an overall




                                                            218
   213   214   215   216   217   218   219   220   221   222   223