Page 323 - Project+
P. 323

9.  C. The total work day duration is eight days. The first day counts as one full day.


    10.  A. Float is always zero for the critical path activities, so early start and late start are
         the same date.

    11.  A. Fast tracking is a technique where you perform multiple tasks in parallel that
         were previously scheduled to start sequentially.

    12.  B. If you didn’t know the quantity and rate, option C or D would be acceptable. In
         this case, you’d use the parametric estimating technique because you do know the
         quantity and rate; 30 hours times 4 miles is a total duration of 120 hours.


    13.  E. Governance gates might include go/no-go decisions, client sign-off, management
         approval, and legislative approval.

    14.  C. The task will take 15 business days to complete (not counting weekends or
                                                                                  nd
         holidays) so that makes the task completion date the 22 . Day 1 counts as the first
         full day of work.
    15.  D. Milestone charts list the major deliverables, key events, or project phases and

         show the scheduled and actual completion dates of each milestone. They may
         include other information, but that information would not be displayed as bar
         charts.

    16.  A. After the WBS is developed, the next step involves creating an activity list that
         describes the activities required to complete each work package on the WBS.

    17.  B. Once the schedule is approved by the sponsor, customer, and stakeholders, the

         schedule baseline is set. The baseline is the approved project schedule and shows
         task start and end dates and resource assignments.

    18.  A. Finish-to-start is the most commonly used logical relationship in network and
         schedule diagrams.

    19.  B. Eliminating Task B leaves you with the longest path through the network
         diagram, which is path A-C-E for a duration of 20 days.

   20.  C. Tasks A, B, D, and G represent the longest dependent path through the network
         diagram at 41 days.



     Chapter 6: Resource Planning and Management


     1.  A. When a new team member is introduced on the project, the team development
         stage starts again at the forming stage, no matter which stage the team was in
         before.


     2.  A. Team-building activities help to build effective and efficient teams, improve
         morale, and build social bonds. Trust building will help form high-performing work
         teams but doesn’t directly lead to building social bonds or effective and efficient
         teams.



                                                            323
   318   319   320   321   322   323   324   325   326   327   328