Appendix 2



               37  814,030

                     Year                 Cash flow            Certainty        RF DF 6%          PV
                                                              equivalent
                     0                   (2,000,000)           1                  1.000       (2,000,000)

                     1                   1,800,000             0.95               0.943       1,612,530
                     2                   1,500,000             0.90               0.890       1,201,500
                                                                                  NPV =         814,030


               38  B, C

                     The strike is a specific risk to Big Co and is therefore an unsystematic risk.


               39  C

                     Ke = Rf + (Rm – Rf) Beta

                     13% = 6% + (10% - 6%) x Beta


                     Beta = 1.75


               40  D

                     An increase in visitor turnover implies either there were more mental health
                     cases for BRAIN to deal with, or they were to deal with them more quickly,
                     neither of which is good for a mental health charity.


               41  A, B, C


                     D would be inappropriate as they are specialists in this area, they just need
                     better supervision.

                     E The bonus payment appears to be part of the problem, increasing would not
                     resolve the issues.

                     F If they removed the bonus completely they may struggle to keep/attract
                     people with the necessary skills.


               42  B

                     The value from the normal tables for 95% is 1.645.


                     The value at risk = Std Dev × Z stat

                     1.645 × 6 = 9.87





               280
   285   286   287   288   289   290   291   292   293   294