READING 20: CAPITAL BUDGETING
    Simulation analysis (or Monte Carlo simulation) results in a
    probability distribution of project NPV outcomes, rather than just a limited
    number of outcomes as with sensitivity or scenario analysis).
                                                                               MODULE 20.2: EVALUATION OF PROJECTS AND DISCOUNT RATE ESTIMATION
     Key steps…

     Step 1: Assume a specific probability distribution for each input variable. For example, we might assume that unit sales are normally distributed with a mean of 100,000
     and a standard deviation of 15,000, unit prices are normally distributed with a mean of $40 and a standard deviation of $5, and so on for each input variable.
     Step 2:  Simulate a random draw from the assumed distribution of each input variable. Our first draw might be unit sales of 85,000, a unit price of $42.00, and so on.

     Step 3: Per Step 1 and 2, calculate the project NPV.

     Step 4: Repeat Step 2 and 3, say, 10,000 times.
     Step 5: Calculate the mean NPV,  standard deviation of the NPV, and the correlation of NPV with each input variable.

     Step 6: Graph the resulting 10,000 NPV


    LOS 20.e: Explain and calculate the discount rate, based on market risk methods, to use in valuing a capital project.

    In the CAPM, risk is separated into systematic and unsystematic components. A diversified investor is compensated for taking on systematic risk, but not unsystematic
    risk. Beta, a systematic risk measure, is appropriate for measuring project or asset risk when a company is, or the company’s investors are, diversified.

                                      EXAMPLE: Using the SML to estimate the discount rate for a capital project: Compute the NPV for a 3-year
                                      project that has a beta of 1.2. The initial investment is $1,000, and the project will generate annual cash flows of
                                      $400. Use a risk-free interest rate of 8% and an expected market return of 13%.


                                      R project  = R + β project  [E(R MKT ) − R ] = 8% + [1.2(13% − 8%)] = 14%
                                               F
                                                                   F
                                      The project’s NPV at a cost of capital of 14% is –$71.35.
                                     Simply using the company’s WACC will overstate the required return for a conservative (low beta) project and will
                                     understate the required return for an aggressive (high beta) project. This is why we had to work out a Hurdle rate for
                                     this specific project!