13 • •• • CHANGE CONTROL AND REQUEST



               All deviation requests for changes to chemical(s), component(s), product(s), tooling, production processes, sub-
               suppliers, manufacturing locations originating with a supplier must be submitted to the Quality and/or
               Purchasing Groups. The request must be initiated utilizing Sun Product’s “Change Request” form and supporting
               justification shall accompany the request. This should include information on costs, impact on performance,
               form, fit and function, reliability and functional test data, field testing (when appropriate), component, process
               and product capability studies and other documentation as deemed necessary after discussions between the
               supplier and Sun Products.


               PRIOR NOTIFICATION IS REQUIRED BEFORE CHANGES ARE MADE.

               If warranted, Sun Products Corporation will facilitate a deviation to permit continued production for the length
               of time needed for the supplier to complete the change.

        14 • •• • PROBLEM RESOLUTION




               I.  NRCCA Process:
                   Upon receipt of nonconforming material Sun may issue the Nonconformance Root Cause Corrective Action
                   (NRCCA) form.  Nonconforming material can be found during incoming inspection, audit, assembly or
                   customer returns.

                   Problems found during pre-production and are considered minor issues; Sun will issue Quality Alerts to the
                   supplier describing the problem.

                   Return Material Authorization (RMA) is required for material that is defective or considered suspect and
                   need to be returned to the supplier.

                   Sun reserves the right to sort suspect material to avoid shutdown of its production lines and return partial
                   rejects to the supplier.

                   Within 72 hours of notification of defective components through NRCCA, suppliers must:

                          •  Address all suspect stock in transit, and any stock at any Sun facilities or Sun Co-packer facilities
                          •  Specify what actions are to be taken
                          •  Inform Sun the plan to replace suspect material
                          •  Identify short term corrective actions
                          •  Send initial corrective action responses

                   Within 14 business days of notification of defects suppliers must:

                          •  Complete root cause investigation and report outcomes and corrective action

                   Within 30 business days of notification of defects suppliers must: