Progress Calls: Countdown to GO-Live!
On your marks
24 Progress Call #10: Objective: No more changes to Holidex XX/XX/2017
hours Implementation Specialist notifies that Holidex®Plus is frozen
12 Progress Call #11: Objective: Migration is Today XX/XX/2017
hours Implementation Specialist reminds POC of Cutover outage 10 am
Get set
Progress Call #12: Objective: Prepare Night Audit XX/XX/2017
4 Implementation Specialist notifies POC that hotel should 6 pm
hours prepare Night Audit, and run all reports in preparation for
Holidex®Plus temporary shut down
15 Progress Call #13: Objective: Ready? XX/XX/2017
mins Implementation Specialist confirms with POC that hotel is ready 9:45 pm
GO!
Progress Call #14: Objective: Cutover has begun
0 hour Implementation Specialist notifies POC that hotel is in Cutover; XX/XX/2017
Implementation Specialist alerts when complete 10 pm