Page 33 - PowerPoint Presentation
P. 33
GO-Live!
24 HOUR CHECKLIST
At 10pm the interface to Holidex®Plus closes and the migration
GO process begins
Once the migration process is complete
We will run the verification process (aka “business checkout”)
to establish that all data has been successfully migrated from
Holidex to GRS
We will run a script in Opera to wipe out all references to
Holidex
Opera will be connected only to GRS even though doing
dual entry
Revenue Management systems point to GRS
Reservations will flow to both Holidex and GRS however
only the GRS is connected to the PMS
We will be on-site and will restart the interface and assist in
inventory balancing
© 2016 IHG 33
R Restricted information intended for IHG colleagues, NOT external vendors