Page 71 - PPAP submission requirements (PPAP check sheet)
P. 71
Form 10.2.1
APPROVAL MINE INSPECTION STANDARD
PART NO. : 49404-A0010-A REF NO.
REASON FOR REQUEST
a; NEW ( ECIXXXX )
PART NAME : TRAY-TOOL-KIT b; ENGINEERING CHANGE ( )
c; PRODUCTION PROCESS CHANGE
d; COST REDUCTION
e; OTHERS
MODEL : M001
CONTENTS : Inspection standard for approval
DETAIL : Please see on the attached pages
We would like to have your approval
ILLUSTRATE :
DATE : 28/1/2020
SUPPLIER(MANUFACTURER) : THAI EPP FOAM CO., LTD.
GM. MANAGER ENGINEER
REPLY SHEET
WE APPROVE YOUR REQUEST
WE APPROVE YOUR REQUEST BY CHANGING SOME ITEMS
WE CANNOT APPROVE YOUR REQUEST
DATE :
MINE MOBILITY CORPORATION CO., LTD (MMC)
SUPPLIER QUALITY DEPT.
GM. MANAGER ENGINEER
ROUTE : SUPPLIER MINE.(SQ COPY) SUPPLIER Rev.1 on 6 Dec 19
SQAM-11-1