Form 10.2.2
MOTHER PLANT MINE MODEL_______M001____________ INSPECTION STANDARD DATE 28/1/2020 PAGE 2 OF 6
PRE-CHECK PART NO. PART NAME FINISHED
DATE / / UNFINISHED
49404-A0010-A TRAY-TOOL-KIT
CASTING FORGING
ROUTE SUPPLIER MATERIAL GENERAL TOL. WEIGHT
THAI EPP FOAM CO., LTD. 295 ± 29.5 g
For Supply Chain
MMR PRE-CHECK
DATE / / MINE
1st Supplier
Part Name TRAY-TOOL-KIT
Part No. 49404-A0010-A
Process Injection
Material EPP 30P BLACK
Supplier THAI EPP FOAM CO., LTD.
MMC Flammability
PRE-CHECKED Material Marking
DATE / /
2nd Supplier
Part Name EPP 30P BLACK
Part No. LBK 30R
Process Raw Material
Material EPP 30P BLACK
Supplier KANEKA
Flammability
COPY NO.
GENERAL MANAGER ENGINEER MINE MOBILITY CORPORATION CO., LTD (MMC) GENERAL MANAGER ENGINEER
MANAGER MANAGER
SUPPLIER DEPT. THAI EPP FOAM CO., LTD.