DEMOLITION PROCESS





                                               NAGPUR METRO








          Shifting/ removal of traffic                     Existing Electrical
                     signals                             Fixtures & utilities to
                                                              be vacated








                                 R &R of Existing Sulabh
                                        Sauchalay
                                                                        Representative of each
                                                                       dept. to remain present
                                                                            throughout the
                                                                          demolition period.




         NOC ‘S REQIURED





                       1             PWD / NHAI Bridges Dept. (Received)




                                      Traffic Police (Agreed in Principle after
                            2             presentation final NOC will be issued.)







                            3          Permission to Dump the Demolished
                                     material. (In Process at collector office)




                       4         Permission to Ply Heavy Vehicles during 24
                                     hours. (to be obtained from Jt. CP Traffic)