DEMOLITION PROCESS
NAGPUR METRO
Shifting/ removal of traffic Existing Electrical
signals Fixtures & utilities to
be vacated
R &R of Existing Sulabh
Sauchalay
Representative of each
dept. to remain present
throughout the
demolition period.
NOC ‘S REQIURED
1 PWD / NHAI Bridges Dept. (Received)
Traffic Police (Agreed in Principle after
2 presentation final NOC will be issued.)
3 Permission to Dump the Demolished
material. (In Process at collector office)
4 Permission to Ply Heavy Vehicles during 24
hours. (to be obtained from Jt. CP Traffic)