DEMOLITION PROCESS










       The first step in the demolition process
       was the removal of the railing present.
       For this purpose gas cutting was done
       to ensure smooth removal. Along with
       this the light poles and other ancillary
       elements were removed.














                                                             The next step was the removal of the
                                                             road sub base. For this purpose,
                                                             breakers were used. As seen in the
                                                             picture, work continued during both
                                                             day and night time which only made it
                                                             possible to complete the demolition
                                                             process       well      before      time.











       The next step was the removal of the
       road sub base. For this purpose,
       breakers were used. As seen in the
       picture, work continued during both
       day and night time which only made it
       possible to complete the demolition
       process       well      before      time.