DEMOLITION PROCESS

                                              APPROACH RAMP REMOVAL
         POLICE





















        Once the deck and the pier is demolished, the next element would be demolition of
        the approach ramp. For this, firstly the compacted reinforced earth was removed with
        the help of excavators. Simultaneously, the exposed RCC Retaining Walls was crushed
        With the help of Jaw crushers. This ensured that the wall did not topple over.