PREPARATORY ACTIVITIES
On the same lines, the basic preparatory plan for dismantling of the Bridge was
prepared in the office of Chief Project Manager/ Reach-1 of NMRCL.
DAYS SR NO. ACTIVITY
1 Road Widening and repairing
Notification to DCP traffic for closure of Road, declaration of
2
No Parking Area on diverted route.
Tie up of availability of demolition machinery, its location and
3
shifting plan by agency
Finalisation of Duty list - Roster for Engineers and circulation
4
to all concerned
5 Arrangement of Signage boards for traffic diversion
Fabrication of barricade boards
6
7 Arrangement of Green Net to control dust in environment
Retention of one pier as monument.
D20 to 8
D11
Preparation of list of occupants around Chhatrapati Bridge and
9
serving letter to them.
Intimation to NMC for deployment of Fire Tender during
10
demolition period.
Advance tie-up for deployment of Ambulance and Medical
11
services.
12 Planning of mobilisation of traffic marshal and its deployment.
Submission of Methodology of demolition of works by M/s
13 NCCL
14 Submission of environment and safety management plan.
Preparation of ID cards for engineers, supervisors, demolition
15
staff agency.