PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION



                   Description      Quantity    planned for   execution  Dismantled   materials   cumulative  Machineries   Manpower   Responsible


             S. no.   of work                         removal              used        used        entity



          DAY -7 :-
                 Cutting with     7 Cum       7 Cum       22221       •Diamon     02
                 wire saw  of                                         d wire
                 Diaphragm 5                                          saw  1      02
                 in small pieces                                      nos.        02
                 and lowering                                         •Crane 1
                 of cut pieces                                        nos.
                                                                      •Jet
                                                                      Blower –
                                                                      01 no.
                 Cutting of Pier    17 cum    17 Cum      22238       •Diamon     02
                 4, toppling                                          d wire
                 down and                                             saw  1      02
                 crushing                                             nos.
                                                                      •Crane 1
                                                                      nos.

          DAY -8 :-

                 Cutting of       17 cum      17 Cum      22255       •Diamon     02
                 Abutment Pier                                        d wire
                 5, toppling                                          saw  1      02
                 down and                                             nos.        02
                 crushing                                             •Crane 1
                                                                      nos.
                                                                      •Jet
                                                                      Blower –
                                                                      01 no.

          DAY -9 & 10

                 Site clearances                                      Loader  -   04
                 and  shifting of                                     02 nos.                                                                              24
                 Debris to the                                        Dumper
                 dumping                                              12 nos.
                 locations

          Note:- Apart from above, requisite capacity of DG set, Traffic marshals/Wardens ( 20 in No.) ,
          lighting arrangement till the completion of work  in addition to the dedicated  technocrats
          would be required for smooth flow of traffic.