PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION


                                                   BAR CHART

                                      Subject:- Sequence of Dismantling of Chhatrapati Bridge
        Sr.                                                               Duration ( In  Days)
                           Sequence of Activities
        No.                                           1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
          Fixing of barricading boards on either side of Bridge
          1.1 Flyover Portion
        1
          1.2 RE wall Portion on Swami Viveka nand Square end.
          1.3 RE wall Portion on Radisson Blu hotel end .
        2    Removal of light poles (i.e. 20 in No.) from bridge portion in all respect.
        3 Dismantling/Crushing and removal of Scrap in flyover portion.
          3.1 Breaking of deck slab and Parapet walls (Span - P1 to P2)- S. V. end
          3.2 Breaking of deck slab and Parapet walls (Span - P5 to P4) - R Blu end
          3.3 Breaking of Span - P2 to P4 including end Girders - complete in all respect
          3.4 Lowering of two girders in Span - P1 to P2, its dismantling & disposal
          3.5 Lowering of two girders in Span - P4 to P5, its dismantling & disposal
          E/W in excavation, Dismantling of RCC structure and removal of Scrap
        4  4.1 RE wall Portion - Swami Vivekanand end
          4.2 RE wall Portion - Swami Vivekanand end
        5 Dismantling/Crushing of Piers & Pier heads and and removal of Scrap
          5.1 Pier no P1
          5.2 Pier no. P5
          5.3 Pier no. P2
          5.4 Pier no. P3
          5.5 Pier no. P4
        6 Cleaning of site, restoration of roads and removal of barricads if required.

          S.      Description of        Name of         Designation      Assistance     Responsible
         no.         activity        person /Entity                       required          entity

                                               People Associated
          1     Over all In-charge       Shri.         CPM/ NMRCL
                                      Ramtekkar
          2      Demolition  In-     Shri K. Sushil   ACPM/ NMRCL
                     charge             Kumar

          3     Engineer In-charge     Shri. B.R.        General
                                       Ramesh,
                                                    Consultant/NMRC
                                                             L
          4       Tech. Co-ordn.      Shri. Ram          Matte &
                                        Matte           Associates.
          5      Police Co-ordn.      Sh. Giri Sir        NMRCL            Traffic    Dy. Commissioner
                                                                          diversion   of Police  (Traffic)
          6      Media Co-ordn.      : Shri Shirish   DGM/PR, NMRCL
                                        Apte,

          7       Site In-charge :      Shri .          A.E, NMRCL
                                      Jaiprakash
                                        Gupta


                                                                                                  32
                          NAGPUR METRO RAIL CORPORATION LIMITED: A JOINT VENTURE OF
                            GOVERNMENT OF INDIA AND GOVERNMENT OF MAHARASHTRA