PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION
BAR CHART
Subject:- Sequence of Dismantling of Chhatrapati Bridge
Sr. Duration ( In Days)
Sequence of Activities
No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Fixing of barricading boards on either side of Bridge
1.1 Flyover Portion
1
1.2 RE wall Portion on Swami Viveka nand Square end.
1.3 RE wall Portion on Radisson Blu hotel end .
2 Removal of light poles (i.e. 20 in No.) from bridge portion in all respect.
3 Dismantling/Crushing and removal of Scrap in flyover portion.
3.1 Breaking of deck slab and Parapet walls (Span - P1 to P2)- S. V. end
3.2 Breaking of deck slab and Parapet walls (Span - P5 to P4) - R Blu end
3.3 Breaking of Span - P2 to P4 including end Girders - complete in all respect
3.4 Lowering of two girders in Span - P1 to P2, its dismantling & disposal
3.5 Lowering of two girders in Span - P4 to P5, its dismantling & disposal
E/W in excavation, Dismantling of RCC structure and removal of Scrap
4 4.1 RE wall Portion - Swami Vivekanand end
4.2 RE wall Portion - Swami Vivekanand end
5 Dismantling/Crushing of Piers & Pier heads and and removal of Scrap
5.1 Pier no P1
5.2 Pier no. P5
5.3 Pier no. P2
5.4 Pier no. P3
5.5 Pier no. P4
6 Cleaning of site, restoration of roads and removal of barricads if required.
S. Description of Name of Designation Assistance Responsible
no. activity person /Entity required entity
People Associated
1 Over all In-charge Shri. CPM/ NMRCL
Ramtekkar
2 Demolition In- Shri K. Sushil ACPM/ NMRCL
charge Kumar
3 Engineer In-charge Shri. B.R. General
Ramesh,
Consultant/NMRC
L
4 Tech. Co-ordn. Shri. Ram Matte &
Matte Associates.
5 Police Co-ordn. Sh. Giri Sir NMRCL Traffic Dy. Commissioner
diversion of Police (Traffic)
6 Media Co-ordn. : Shri Shirish DGM/PR, NMRCL
Apte,
7 Site In-charge : Shri . A.E, NMRCL
Jaiprakash
Gupta