Page 36 - PowerPoint Presentation
P. 36
PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION
Description Quantity planned for execution Dismantled materials cumulative Machineries Manpower Responsible
S. no. of work removal used used entity
DAY -5 :-
Cutting with 7 Cum 7 Cum 21898 •Diamon 02 NMRCL
wire saw of d wire & M/s
Diaphragm 3 in saw -1 02 NCC
small pieces nos. 02
and lowering •Crane 1
of cut pieces nos.
•Jet
Blower -
01
Cutting of Pier 17 cum 17 Cum 21915 •Diamon 02 NMRCL
2, toppling d wire & M/s
down and saw 1 02 NCC
crushing nos.
•Crane 1
nos.
Respective 275 cum 275 cum 22190 Jaw 06 NMRCL
exposed top Crusher & M/s
RE wall 2 nos. NCC
crushing
DAY -6 :-
Cutting with 7 Cum 7 Cum 22197 •Diamon 02 NMRCL
wire saw of d wire & M/s
Diaphragm 4 in saw 1 02 NCC
small pieces nos. 02
and lowering •Crane 1
of cut pieces nos.
•Jet
Blower –
01 no.
Cutting of Pier 17 cum 17 Cum 22214 •Diamon 02 NMRCL
3, toppling d wire & M/s
down and saw 1 02 NCC
crushing nos.
•Crane 1
nos.
36
NAGPUR METRO RAIL CORPORATION LIMITED: A JOINT VENTURE OF
GOVERNMENT OF INDIA AND GOVERNMENT OF MAHARASHTRA