PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION
Description Quantity planned for execution Dismantled materials cumulative Machineries Manpower Responsible
S. no. of work removal used used entity
DAY -4 :-
Crushing of 290 Cum 290 16792 •Jaw 12 NMRCL
central Span Cum Crusher 4 06 & M/s
no 4 nos. NCC
•Diamond
floor saw -
02 nos.
Cutting with 7 Cum 7 cum 16799 •Diamond 02 NMRCL
wire saw of wire saw 1 & M/s
Diaphragm 2 nos. 02 NCC
in small pieces •Crane 1 02
and lowering nos.
of cut pieces •Jet Blower
– 01 no.
Cutting of 17 Cum 17 16816 •Diamond 04 NMRCL
Abutment Pier Cum wire saw 2 & M/s
1, toppling nos. 02 NCC
down and •Crane 1
crushing nos.
Ramp removal 4800 Cum 4800 21616 •Excavator 4 08 NMRCL
lower 1/4 th Cum nos. 100 & M/s
layer- North •Dumper 50 NCC
and South end nos.
Respective 275 Cum 275 21891 •Jaw 04 NMRCL
exposed top Cum Crusher -2 & M/s
RE wall nos. NCC
crushing