PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION






            Planning with regard to ease the traffic movement and proper barricading was done
            efficiently so as to avoid any mishaps or accidents. The entire demolition area was
            demarcated off use well before time. This area is located in a very high traffic zone
            and hence taking utmost care during diversion was imperative. The local residents
            abiding in the nearby vicinity were provided with parking tokens. These tokens were
            necessary in order to be granted access inside the demolition area. Traffic marshals
            were present round the clock to ensure smooth diversion of traffic and also to assist
            the residents to commute effortlessly. Proper signage were used and put up well in
            advance to make the public more aware and alert. They could also plan their
            journey beforehand keeping in mind the temporary inconvenience. The public too
            cooperated with NMRCL aptly and the response was fitting. In a nut shell, various
            steps were taken by NMRCL to make this transition a hassle free move