PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION


















































            The total outline planning of work started 50 days before the actual commencement
            in the office corridors of top management officials of Nagpur Metro Rail Corporation
            Limited (NMRCL). There were series of meetings at different levels- inter and intra
            NMRCL so as to resolve some very typical issues such as Traffic Diversion, freezing
            the Work Methodology, permission of working at night, support of local Municipal
            Corporation and other related agencies. In the lines of decisions of top
            management, middle level working committee meetings was chaired by the Chief
            Project Manager of the work and minute detailing and tuning up of all decisions and
            practical implementations was continuously deliberated for hours to gear up the
            work.