PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION
Description of planned for Dismantled Cumulative Machineries Manpower Responsible
S. no. work Quantity execution Qty. Of materials removed Likely rqd. Likely required entity
DAY -1 :-
Lighting post and 20 20 Hydra – 1 MSEB,
Services removal no. NMRCL
(Entire Bridge)
Crash barrier 200 200 Cum 200 •Jaw 06 NMRCL
removal - (North Cum Crusher – & M/s
Ramp + one span 02no. 02 NCC
and South with •Jet
Half portion of blower
Bridge span) 01 no.
Crushing of 290 290 Cum 490 •Jaw 06 NMRCL
Girder in central Cum Crusher – & M/s
Span no 1. 02no. 02 NCC
•Jet
blower 06
01 no.
•Diamon
d floor
saw -02
nos.
Ramp removal 4800 4800 Cum 5290 •Excavato 08 NMRCL
top ¼ th layer - Cum r -04 no & M/s
North and South •Dumper 100 NCC
end - 50 nos.
Respective 275 275 Cum 5565 •Jaw 06 NMRCL
exposed top RE Cum Crusher - & M/s
wall crushing 2 nos. 02 NCC
•Jet
blower
01 no.
Shifting of Debris •Dumper 100 NMRCL
to dumping yard. – 50 No. & M/s
NCC