PREPARATIONS: 20 DAY PLAN TO 15 DAY EXECUTION


                 Description of         planned for   Dismantled   Cumulative  Machineries   Manpower    Responsible




           S. no.   work             Quantity    execution  Qty. Of   materials   removed  Likely   rqd.  Likely   required   entity



         DAY -1 :-
               Lighting post and   20          20                     Hydra – 1                MSEB,
               Services removal                                       no.                      NMRCL
               (Entire  Bridge)

               Crash barrier       200         200 Cum      200       •Jaw         06          NMRCL
               removal - (North    Cum                                Crusher –                & M/s
               Ramp + one span                                        02no.        02          NCC
               and South  with                                        •Jet
               Half portion of                                        blower
               Bridge span)                                           01 no.
               Crushing of         290         290 Cum      490       •Jaw         06          NMRCL
               Girder in central   Cum                                Crusher –                & M/s
               Span no 1.                                             02no.        02          NCC
                                                                      •Jet
                                                                      blower       06
                                                                      01 no.
                                                                      •Diamon
                                                                      d floor
                                                                      saw -02
                                                                      nos.
               Ramp removal        4800        4800 Cum     5290      •Excavato    08          NMRCL
               top ¼ th layer -    Cum                                r -04 no                 & M/s
               North and South                                        •Dumper      100         NCC
               end                                                    - 50 nos.
               Respective          275         275 Cum      5565      •Jaw         06          NMRCL
               exposed top RE      Cum                                Crusher -                & M/s
               wall crushing                                          2 nos.       02          NCC
                                                                      •Jet
                                                                      blower
                                                                      01 no.

               Shifting of Debris                                     •Dumper      100         NMRCL
               to dumping yard.                                       – 50 No.                 & M/s
                                                                                               NCC




                                                                                                  33