Control of Industrial Major Accident Hazards (CIMAH) Report   Page       21
                                               Ranhill SAJ Sdn. Bhd.                    Revision      01
                                  Part D: Information on the Potential Major Accident   Date        Aug 2019


               protective  equipment  (PPE)  for  the  personnel  who  are  to  perform  work  at  site.
               Besides,  the  Company  emergency  response  team  is  required  to  use  the  self-
               contained breathing apparatus (SCBA) in the event of chlorine leak. The SCBA is
               subject to periodical inspection and testing by the service vendor.

               There is emergency shower and eyewash, and first aid kit as part of the facility/plant
               lifesaving equipment.

               D.3.2.9 Hazard & Effect Prevention, Control and Mitigation

               Based on the Company’s prevention, control and mitigation measures as described
               above,  a  structured  hazard  and  effect  management  process  (HEMP)  was
               undertaken to demonstrate that the control measures are adequate, sufficient, and
               reliable to mitigate and minimise the risk of the major accident events to as low as
               reasonably achievable (ALARA).

               Hazards and Effect Prevention, Control and Mitigation is provided in Figure D 3.1