4.2.3 Removal of Existing Installations              considered for re-use where it is in good condition
                                                     and complies fully with the requirements of the
The Contractor shall strip out and dispose of any    project and the current IEE regulations.
existing redundant electrical installations. This
should normally include everything, back to
the meter. Existing equipment should only be

4.2.4 Mains Distribution                                 the distribution board cover.
                                                     •	 Clearly indicate in typed script, circuit
•	 Liaise with the electrical distribution
    company, as necessary, to confirm or                 identification number, cable size, circuit
    determine that the main supply head fuse             breaker rating and a description of the item
    is rated at 100 amps, if single phase. Advise        and area supplied by the circuit.
    DPG if this is not the case.                     •	 Note that the Air Conditioning and Coldroom
                                                         circuits MUST utilise Type 3 breakers to cope
•	 Except in exceptional circumstances, DPG              with start loads.
    will normally have arranged for any existing     •	 Carry out the installation of an earthing
    single phase incoming supply and/or meter            system in accordance with BS7671 and
    to be upgraded to a 3-phase supply and               BS7430.
    meter.                                           •	 Provide a main earth bar at the incoming
                                                         service position, together with a clean earth
•	 Wherever a 3-phase meter is installed, then           bar for computer circuits.
    the shop installation MUST be arranged to        •	 Ensure that all items of fixed metal equipment
    take balanced loads from all 3 phases.               are correctly earth bonded.
                                                     •	 Ensure that the phases are correctly
•	 Supply and install a new MCB distribution             balanced.
    board. This shall be suitably sized to meet the
    requirements of the installation and allowing    Wiring Installation
    25% spare capacity within the board for          •	 Final circuit wiring shall be carried out using
    future expansion or alteration.
                                                         concealed BASEC certified flat cabling to
•	 Normally, install the board adjacent to               BS6004 or LSZH to BS7211.
    the incoming main and metering, unless           •	 Ensure that all cables are fixed at least
    otherwise agreed in specific circumstances.          200mm from hot water pipes.

•	 Install the board so that any covers/doors
    may be opened on their hinges and do not
    have to be lifted off to gain full access. In
    accordance with Amendment No. 1: 2011.
    of 17th Ed IEE Regs.

•	 Identify every out-going way with a
    renewable circuit chart in a transparent
    plastic envelope permanently fitted inside