Page 80 - B8773-AEW-XX-XX-PP-A-0001_[P1]_Contractors Manual
P. 80

4.5 Drainage and Piped Services

4.5.1 Hot Water                                        •	 The boiler shall be installed in accordance
                                                           with BS 5546 Specification for Installation
Hot water shall normally be provided by a gas              of Gas Hot Water Supplies for Domestic
fired, room sealed, instantaneous, condensing              Premises and manufacturers instructions.
multi-point combi water heater, ( Worcester
Bosch Greenstar 28i Junior, or equal or better)        •	 The hot water installation shall be carried out
located at high level in the position shown                in light gauge copper tube Table X and shall
on the drawing and installed to comply with                be designed and installed in accordance
manufacturers and appropriate building                     with BS 6700 1997 Specification for Design
regulations requirements. This boiler series MUST          Installation Testing and Maintenance of
be used to ensure compliance with Part L2 of               Services Supplying Hot Water for Domestic
Building Regulations.                                      Use within Buildings and their Curtilages.
•	 Note that the boiler MUST be installed so that
                                                       •	 Pipework shall be concealed as far as
    a minimum of 600mm clear space is left in              possible but not hidden inside stud walls etc.
    front of it for servicing. This includes ensuring
    that no shelving or other obstructions             •	 Any voids which are used for pipe runs must
    are subsequently installed to reduce this              be ventilated.
    clearance.
•	 The boiler heating circuit will supply a low        •	 Gas pipework which is visible to the
    pressure hot water heater coil installed in the        customers should be painted white and
    fresh air intake duct ( supplied and installed         marked at appropriate intervals with yellow
    by others). The plumber must connect the               “GAS” tape. Other gas pipes should be
    hot water supply to the heater coil via a              painted yellow ochre.
    thermostat and 3-way valve (supplied by
    others).                                           •	 Gas pipework shall terminate with an
•	 The plumber must install isolation valves on            appropriate sized yellow handle stop-cock,
    the flow and return pipework to the heater             adjacent to each appliance, and earth
    coil so that the coil can be isolated in case          bonded as required.
    of a problem.
•	 A drain-off point should also be fitted to the      •	 All water pipework in unheated areas shall
    heater coil circuit.                                   be insulated against frost with insulation of a
•	 Any pipework, return loops, or similar, needed          suitable thickness.
    to ensure the safety of the boiler must be
    installed using appropriate pipework and           •	 The insulation, adhesive, tape and all other
    fittings..                                             installation materials shall be suitable for use
•	 The gas supply pipe for the boiler should be            in food premises.
    not less than 22mm.
•	 The gas supply pipe for the boiler MUST be          •	 All exposed pipework shall be installed with
    routed so that it is NOT disconnected from             sufficient clearance between the pipe
    the gas supply in the event of the solenoid            (or insulation surface) and adjacent walls,
    valve cutting supplies to the ovens.                   pipes, cables, equipment etc. to allow
                                                           proper cleaning.

                                                       •	 All valves shall be WRC approved,
                                                           manufactured from non-dezincifiable brass.

                                                       •	 A gas installation certificate must be
                                                           provided on completion.

4.5.1  Hot Water                                       3 February 2016
   75   76   77   78   79   80   81   82   83   84   85