P. 43
be secured into position using black low modus A F T
The counter should be installed so that the
face of the tiles are flush with the face of the
adjacent MDF wall.
The counter top(s) should be installed to provide
a 28mm overhang to the customer side.
The sneeze glass is to be secured in position
in recessed channels. The base channel is
recessed within the slap table front and the
head channel is fixed flush within the suspended
ceiling. A side location channel should also be
set within the white (feature) wall tiles.
The frosted glass panel must be inset into the
channel provided in the counter top. Glass to
sealant. Frosted side to be facing the computers,
customer side to be the plain polished glass
face. D R
2.7 Counters 3 February 2016