Page 332 - Installation Training Binder FIT1-3
P. 332

Step 6

                   Application

                          Before  starting  flooring  application,  it  is  recommended  that  the  installer
                          read all available safety data including, but not limited to, OSHA approved
                          material safety data sheet, product data sheet and backup label.


                   Mixing

                          Pre-mix Part A (resin) for about 30 seconds using a jiffy mixer. Pour Part B
                          (hardener) into the Part A pail and mix thoroughly for 2 minutes.  Pot life is
                          approximately 10 minutes @ 70 F in the container.
                                                            o







                                                        Jiffy Mixer

                                    (Not included, available at any local hardware store)

                   Installation

                                                                                        o
                          Do not apply epoxy when surface temperature is below 35 F.

                          For application, the epoxy base coat/sealer resin-hardener should be at a
                                                        o
                          minimum temperature of 70  F.

                          Always pour the material as soon as it is blended.  In the container,
                          the  pot  life  is  approximately  10  minutes.  The  working  life  once
                          poured is approximately 30 minutes.

                          Always spread immediately after pouring.  Cold concrete temperatures will
                          cause  a  viscosity  increase;  the  longer  the  cool  surface  contact  before
                          spreading to 15 mils, the more increasingly difficult it becomes.

                          Add Part B to Part A and mix thoroughly.  Spread the Part A and B mixture
                          with (3/8”) nap roller at a rate of 50 square feet per gallon (30 mils).

                                  NOTE: Additional material will be required if surface is rough.

                          Allow  to  cure.    The  cure  is  directly  related  to  the  temperature.  See  the
                          following schedule:

                                                                 o
                          35 F- 7 days                        60 F- 48 hours
                             o
                             o
                          40 F- 5 days                        70 F- 36 hours
                                                                 o
                             o
                                                                 o
                          45 F- 4 days                        80 F- 24 hours
                                                                 o
                             o
                          50 F- 3 days                        90 F- 16 hours
                   EnviroGuard  800-206-9884          Fax  909-624-1772               www.enviroguard.com
                   11/2007 rev. B              Condor System Setup Instructions                 Page - 12 -
   327   328   329   330   331   332   333   334   335   336   337