Page 373 - Installation Training Binder FIT1-3
P. 373

Step 4b

                   Battery Stack Installation

                          Always check for rebar or underground obstructions before drilling!

                          Assemble the VRLA stack according to the battery manufacturer
                          instructions.  Be sure to place the included acid-resistant support plates
                          under feet to help prevent tearing the liner.  Center the VRLA stack on
                          the inside of the liner.  Be very careful not to tear the liner by shifting the
                          VRLA stack.  The liner should extend beyond the VRLA stack evenly on all
                          sides (Figure 5). The containment system may have been sized to allow a
                          larger spacing in the front to allow access to the terminals.  Be sure to allow
                          at least 1” spacing in the back and sides.  Verify aisle width and distance
                          needed from wall.  Check to ensure that distances from the Barrier Wall
                          comply with local codes.  Mark the locations of the holes to be drilled for the
                          battery stack.  Drill holes for battery stack anchor bolts.  Clean holes and
                          remove debris.

                                                                 Centering the Stack on the
                                                                 liner is very critical. If
                                                                 another installer is
                                                                 responsible for placing the
                                                                 Stack, make sure it’s
                                                                 centered prior to drilling.


                                    Figure 5

                          If bolting VRLA stack to the ground, coat the anchor bolt with supplied
                          sealant before placement. Insert anchor bolt through washer (Figure 6). Run
                          a bead of supplied sealant around VRLA stack footprint, anchor bolts and
                          any open welds on VRLA stack that would allow liquid to seep under the
                          stack footprint.

















                                                               Figure 6




                   EnviroGuard  800-206-9884     Fax  909-624-1772               www.EnviroGuard.com

                   03/01/2017 Rev. G            Hawk System Setup Instructions                         10