Depending on the size of the containment, some Hawk systems may include
retainer brackets (HWK-HCAL or HWK-HCAS). (If the containment system does
not contain retainer bars, skip to next step.) Slide “H” channel into retainer bracket
as shown in Figure 11. Lay retainer bars as shown in Figure 12.
Figure 11
Retainer bar For
Systems over 96”
Figure 12
When installing multiple cabinets, align barriers the “H” channels as shown
in CAD Diagram. Align “H” channels as close as possible with cabinet joints
to allow access to cabinet door (Figure 13). Barrier sizes and “H” Channel
spacing must be defined and requested at time of ordering.
UPS Battery Battery
Cabinet Cabinet Cabinet
Figure 13
“H” Channels are aligned with cabinet joints to enable
“Hawk” Barriers to be removed to allow cabinet doors to
open, when requested at time of ordering.