Depending on the size of the containment, some Hawk systems may include
                   retainer brackets (HWK-HCAL or HWK-HCAS).  (If the containment system does
                   not contain retainer bars, skip to next step.)  Slide “H” channel into retainer bracket
                   as shown in Figure 11.  Lay retainer bars as shown in Figure 12.














                                                          Figure 11



                  Retainer bar For

                  Systems over 96”








                            Figure 12


                          When installing multiple cabinets, align barriers the “H” channels as shown
                          in CAD Diagram.  Align “H” channels as close as possible with cabinet joints
                          to allow access to cabinet door (Figure 13).  Barrier sizes and “H” Channel
                          spacing must be defined and requested at time of ordering.




                               UPS             Battery          Battery
                             Cabinet          Cabinet           Cabinet









                                                                                      Figure 13




                                        “H” Channels are aligned with cabinet joints to enable
                                        “Hawk” Barriers to be removed to allow cabinet doors to
                                        open, when requested at time of ordering.

                   EnviroGuard  800-206-9884     Fax  909-624-1772               www.EnviroGuard.com

                   03/01/2017 Rev. G            Hawk System Setup Instructions                         13
   371   372   373   374   375   376   377   378   379   380   381