Page 46 - STARTER KIT SHIFT ENGINEER
P. 46
STARTER KIT | Shift Engineer
Task 14: Summarize reports during the shift
OPERATING PROCEDURES STANDARD(s)
Prior to logging out after shift reports must be updated and
summarize including but not limited to:
1. Consumption Reports (Electricity & Water)
2. KPI (Daily Accomplishments of Painter, Laborer,
Carpenter, Plumber and Handyman)
3. Prepare turnover report of ongoing projects and
pending Job Orders
Task 15: Commissioning and quality checking accomplished JOR.
STEP(S) STANDARD(S)
1. After JOR completed commissioned or checked the No incidence of accomplished JOR are not checked and
quality of worked. commissioned.
2. Assess and make evaluation. No incidence of back job on accomplished JOR.
3. Report recommendation to Housekeeping and Front
Office Department.
Task 16: Reading of water and power consumption
STEP(S) STANDARD(S)
1. 12mn- Get the meter reading of water and power. Power and water cost daily are recorded daily.
2. Record all reading in daily cost monitoring of power
and water.
3. Report to Hotel Engineer all unusual reading for the
day.
4. Report all usual incidents in power and water
concern (if any).
Task 17: Handle of engineering tool and equipment.
STEP(S) STANDARD(S)
1. Daily checking of engineering tools/equipment. All equipment and tools are properly working and secured.
41