               Phase V – Bidding                                  Phase VI – Construction Contract Administration


               Upon receiving your notice to proceed with this    Once the Agreement with the single general contractor is
               phase, we will assemble the construction documents   executed, Bernardon will provide construction contract
               and incorporate them into one (1) package for      administration services for the project.  At this time, we
               distribution to the bidders.  We understand that you   anticipate substantial completion of the building within
               intend to competitively bid the construction contract   fourteen (14) months of the General Contractor’s Notice
               to qualified general contractors.  We anticipate that   to  Proceed.    During  construction  we  will  perform  the
               up to five (5) qualified contractors will be invited   following services:
               to bid.  We will issue the contract documents to the
               prospective bidders and we will issue addenda as        ■ Bernardon will attend one (1) pre-construction
               required.                                              meeting and up to twenty-four (24) construction
                                                                      progress meetings to observe the progress of
               Upon receipt of the bids, we will conduct one (1)      the work and to answer questions regarding the
               meeting to review the bid proposals with you.  At      construction.  The Structural Engineer will visit
               the conclusion of this analysis, we will assist your   the site four (4) time.   The MPEFP Engineer will
               legal counsel in the preparation of the Agreement      visit the site four (4) times including the punch list
               between you and a single general contractor for the    visits.  We will prepare field reports following each
               construction phase of this project.                    visit to the site.
                                                                       ■ On  a  monthly  basis, we  will  review  the  General
               The following is an outline of the bidding services:   Contractor’s Application for Payment in the form of
                                                                      the AIA Document G702 for the scope of completed
                     ■ Release and distribute documents for bidding;  work that is included as part of our agreement.
                     ■ Participate in a Pre-Bid conference;            ■ We will respond to the General Contractor’s Requests
                     ■ Review questions from bidders and prepare      for Information (RFIs) via written or graphic means
                    addenda;                                          to interpret the intent of the contract documents.
                     ■ Attend one (1) meeting to evaluate the bids with     ■ We will provide shop drawing review of architectural,
                    the Lindenwold Fire Department;                   structural, mechanical, plumbing, and electrical
                     ■ Prepare a Notice of Intent to Award, and       components as required by the contract documents.
                     ■ Assist your legal counsel in the preparation   One (1) review of each required submittal plus
                    of AIA Document A-101 Standard Form of            one (1)  follow-up review is included provided the
                    Agreement Between Owner and Contractor.           submittal is made in accordance with the contract
                                                                      documents.
               We anticipate completion within six (6) weeks of the     ■ After the General Contractor provides their record
               notice to proceed for this phase.                      of completed punch list or incomplete or deficient
                                                                      items, we will review and supplement their punch
                                                                      list as necessary.
                                                                       ■ We will prepare and execute the Certificate of
                                                                      Substantial Completion and assist in the receipt of
                                                                      written warranties and project close-out documents.