Page 388 - Bahrain Gov Annual Reports (III)_Neat
P. 388

96

                           STATE ENGINEER'S REPORT, 1365 (1946)
                   Electricity Undertaking.—The installation of a new MIRRLEES-B.T.H. generating set
              of 206 kW capacity was completed on 6th April, 1946 and after preliminary running and final adjust­
              ments, was put on load on 13th April, 1946. His Highness Shaikh Sulman visited the Power House
              Station on this date and officially started up the engine' by opening the compressed air starting
              mechanism. This generating set has operated successfully to date and has carried loads representing
              90% of its rated output on numerous occasions for continuous daily periods between 7 and 24 hours.
              Owing to the delay in obtaining the water pumps and cooler, to enable a closed circuit cooling system
              to be used, it has run on an open circuit using an Heenan and Froude water cooler. This has resulted
              in daily distilled water consumptions up to 1,140 galls, for 24 hours running as compared with a con-
              sumption of 90 galls, when using a closed circuit under similar load and duration conditions. The
              distilled water has had to be transported by road from the Naval Base at Jufair in a 500 gallon capacity
               tanker, and the cost of this, together with the production costs has considerably increased electricity
              generating costs.
                   As the new engine is of the high speed type and unable to operate when using the local raw
               water, no alternative to the procedure employed was possible. There have been no shut downs during
              the hot weather season, excepting on rare occasions for short periods and for reasons entirely beyond
              control. The maximum load recorded was 400 kW. and the load variation during the months April-
               October was between 330-400 kW. The maximum output of the plant during this period was
               425 kW, which allowed a negligible margin of safety.
                    Power Distribution.—The present distribution system, which was planned when the first
               two generating sets were installed in 1349, requires to be modified. The positions of the step down
               transformers are not on the present centres of gravity of the respective loads, and their capacities are
               insufficient. The High Tension feeder cables to the transformers are also, in some cases, of insufficient
               capacity. This is the result of an increase in the generating output from 200 kW to 606 kW between
               1349 ^4 the end of 1365 to supply an additional 1,474 consumers between the same dates. Four
               of the original metal kiosks which house step down transformers and their associated switchgear
               require to be dismantled and replaced by stone work buildings capable of accommodating larger capacity
               transformers. This work has been planned for completion during 1366. Four power line standards
               have had to be .replaced owing to damage caused by motor vehicles and three owing to excessive
               corrosion which rendered them unsafe. Three H.T. line breakages occurred without serious damage
               and also several L.T. line breakages. In each instance the breakage was the result of corrosive action
               and old age.

                    Extensions to Power Supply.
                      (а)  The B.O.A.C. rest house new sub-station of 100 kVA capacity supplying power for
                           lighting and air conditioning was connected during April.
                      (б)  A new sub-Station of 50 kVA capacity was erected near to the fish market to provide
                           power for four new flour mills.
                      (c)  A low tension cable supply was run from the power house to the new stores and machine
                           tool workshops.
                      (d)  A new sub-Station to house an additional 50 kVA step down transformer was erected
                           in Muharraq. This is not yet connected to the H.T. cable as the transformer ordered
                           in England has not arrived.

                    New Load.—Additional connections during the year amounted to 265*800 kW as compared
               with 89*500 kW during 1349*  Details are as follows:—
                      I. Light, fan, and plug points                  64*866 kW.
                      2. Power
                           (а)  4 Flour Mills              45*760 kW.
                           (б)  Government Workshop Machine Tools 60*676 kW.







                                                                                             1
   383   384   385   386   387   388   389   390   391   392   393