Ryan T. Moore PE, TE




                         by the USACE. This project involved extensive public input and coordination
                         process with a technical advisory panel consisting of political and management
                         members  and  an  urban  design  team  from  local  community  representatives.
                         Responsible for the design of the structure, which included submerged driven
                         pile foundations, pedestrian overlooks, and extensive architectural treatment.


                         Interstate  80/West  El  Camino  Interchange  improvement  Project  Study
                         Report, Sacramento, CA
                         Project Manager for a Project Study Report for an interchange reconstruction at
                         West El Camino Avenue on Interstate 80.  Deficiencies included off ramps which
                         create unacceptable mainline queuing in the PM peak hour, two lane structure
                         connecting to a 4 lane local road, and a lack or bicycle and pedestrian facilities
                         on the structure.  The structure is also too low for ultimate mainline buildout,
                         which included new HOV lanes in the current median.  The PSR, which included
                         a  Preliminary  Environmental  Assessment  Report,  identified  a  complete
                         reconstruction of the interchange into a variant of a type L-9 interchange, with
                         “squared” loop ramps to enhance safety for bikes and pedestrians.  The under
                         clearance also necessitates a replacement of the bridge