Page 15 - GLNG Week 40
P. 15

GLNG                                            AFRICA                                                GLNG


       Angola reports oil output up slightly in August





        PERFORMANCE      ANGOLA’S National Agency of Petroleum,  mmcf (2,434 mcm), or 2,773 mmcf (78,523 cubic
                         Gas and Biofuels (ANPG) said last week that  metres) per day, recorded in the same month of
                         the country had seen crude oil production rise  the previous year.
                         slightly in the month of August.       The agency further stated that the Angola
                           In a press release, ANPG stated that Angolan  LNG plant in Soyo, a town in northern Angola,
                         oilfields had yielded a total of 39.265mn bar-  turned out 4.6mn boe (151,371 boepd) of LNG
                         rels of crude in August, equivalent to 1.265mn  and other fuels in the month of August. This con-
                         barrels per day. This was 0.42% above the figure  sisted of 3.78mn boe (121,984 boepd) of LNG,
                         of 1.26mn bpd reported for the same month of  427,044 boe (13,776 boepd) of propane, 283,910
                         2019, it said.                       boe (9,158 boepd) of butane and 200,070 boe
                           The agency also noted that production of liq-  (6,454 boepd) of condensate.
                         uid hydrocarbons – that is, crude oil, gas con-  Angola LNG is a consortium formed by the
                         densate and LPG – had amounted to 39.958mn  national oil company (NOC) Sonangol, BP (UK),
                         barrels of oil equivalent (boe) in August, equiv-  Chevron (US), Eni (Italy) and Total (France). Its
                         alent to 1.289mn boe per day (boepd). It did not  gas liquefaction plant is capable of turning out up
                         provide a comparative figure from last year.  to 5.2mn tonnes per year (tpy) of LNG.
                           ANPG went on to say that Angola had   ANPG also said that the Cabinda Association
                         extracted some 94.228mn cubic feet (2.668mn  had extracted 519,222 boe of LPG, equivalent
                         cubic metres) of associated gas, equivalent to  to 16,749 boepd, in August. This group – which
                         3.04 mmcf (86,083 cubic metres) per day. This  includes the US major Chevron as well as Eni,
                         represented a rise of 9.63% on the figure of 85,963  Total and Sonangol – is the developer of Block 0.™





       Golar LNG, BP strike agreement on




       delivery date for Gimi FLNG vessel





        PROJECTS &       BERMUDA-REGISTERED  Golar LNG  reduce and re-profile its capital spending com-
        COMPANIES        revealed in a statement last week that it had  mitments for 2020 and 2021.” Later, it conceded
                         struck a deal with BP (UK) on setting a new  that it had no choice but to revise its work sched-
                         target date for the conversion of the Gimi LNG  ule, citing the impact of lockdowns in Singapore.
                         tanker into a floating LNG (FLNG) unit for the   Since then, BP and Golar LNG have been
                         Greater Tortue/Ahmeyim project offshore Mau-  working to draw up a new work plan. They have
                         ritania and Senegal.                 now wrapped up talks on the matter and have
                           The new deadline will be nearly a year  agreed to preserve the original 20-year term of
                         behind the original, the statement said. “The  the charter, according to the latter company’s
                         revised project schedule will result in the target  statement.
                         connection date for the converted [FLNG] ves-  Additionally, BP has lifted its declaration of
                         sel Gimi, previously scheduled for 2022 ... being  force majeure, Golar LNG noted. These develop-
                         extended by 11 months,” the statement said.  ments are “expected to facilitate the conclusion
                           The two companies had originally signed a  of ongoing discussions with both engineering,
                         20-year charter for the vessel in February 2019.  procurement and construction [EPC] contrac-
                         At that time, they said they hoped to finish the  tors and lending banks regarding the adjustment
                         $1.3bn conversion project in time for the Gimi  of construction and financing schedules respec-
                         FLNG unit to begin liquefying gas from the  tively,” it added.
                         Greater Tortue/Ahmeyim block in 2022. But   UK-based BP is leading development efforts
                         in April 2020, BP declared force majeure on the  at the Greater Tortue/Ahmeyim block, which
                         project, saying it wanted to delay receipt of the  straddles the maritime border between Senegal
                         vessel for 12 months in light of the coronavirus  and Mauritania. The super-major and its part-
                         (COVID-19) pandemic.                 ners intend to extract hydrocarbons from the
                           Golar LNG criticised this move, saying it did  ultra-deepwater block using a floating produc-
                         not expect the pandemic to lead to such a long  tion, storage and off-loading (FPSO) vessel. The
                         delay. However, it also began discussions with  FPSO will then transfer gas to the Gimi FLNG,
                         Singapore-based Keppel, its main contractor,  which is capable of turning out about 2.5mn
                         citing a need “to re-schedule activities in order to  tonnes per year (tpy) of LNG.™



       Week 40   09•October•2020                www. NEWSBASE .com                                             P15
   10   11   12   13   14   15   16   17   18   19   20