Page 32 - Mercy College_BarrandBarr_7.26.17
P. 32

Mercy College                                                                                                 DD Estimate
 Victory Hall Addition / Renovation                                                                              07/26/17
 Dobbs Ferry, New York
                                                    ESTIMATE DETAIL
   LINE     CODE                       ELEMENT DESCRIPTION                QUANTITY    UNIT  UNIT RATE      TOTAL


        4   01000   General Requirements
        5           OSHA Protection                                               10  MO         $200.00         $2,000
        6           Scaffolding                                                                                 w/trades
        7           Lull                                                                                        w/trades
        8           Temporary water for construction use                                                        w/trades
        9           Temporary gas consumption w/permanent system                                                w/trades
       10           Temporary heating units                                                                       NIC
       11           Fuel for temporary heating units                                                              NIC
       12           Temporary power consumption for 10 months                                                     NIC
       13           Safety carpenter                                               9  WK        $2,362.40       $21,262
       14           Laborer                                                       25  WK        $2,010.40       $50,260
       15           Safety material                                                                             w/trades
       16           Site construction fence w/gates                             1,500  LF          $8.00        $12,000
       17           Temporary walks/access                                         1   LS       $7,500.00        $7,500
       18           Traffic control & flagging                                                                  w/trades
       19           Police details                                                                             By owner
       20           Dumpsters                                                     40   EA        $500.00        $20,000
       21           Indoor air quality control testing                                                            NIC
       22           Testing of paint, SPFP, ACT & Carpet                                                          NIC
       23           Final cleaning (including interior & exterior glass)                                       By owner
       24   01000   General Requirements                                                                       $113,022
       25
       26   02000   Abatement
       27           Abatement per Pennoni Associates Budgetary Cost Estimate       1   LS     $329,064.00      $329,064
       28   02000   Abatement                                                                                  $329,064
       29
       30   02100   Selective Demolition
       31           02 4119 Selective Demolition
       32            West Entrance
       33              Remove Existing Entrance Storefront Doors                   3   EA        $160.00          $480
       34              Remove Planter                                              1   EA        $480.00          $480
       35              Remove Windows                                             13   EA        $175.00         $2,275
       36              Remove Brick Veneer                                       400   SF         $15.00         $6,000
       37              Remove Light Guage Framing                                775   SF          $5.50         $4,263
       38              Remove Structural Steel                                     1   LS       $2,880.00        $2,880
       39              Shore on interior side on 2 floors                          1   LS       $7,500.00        $7,500
       40              Remove Ceilings 1st Floor                                 510   SF          $1.50          $765
       41              Remove Ceilings 2nd Floor                                 718   SF          $1.50         $1,077
       42              Remove Flooring 1st Floor                                 544   SF          $2.50         $1,360
       43              Remove Flooring 2nd Floor                                 664   SF          $2.50         $1,660
       44              Remove Portion of Existing Parapet for new Building Elements  36  LF       $45.00         $1,620
       45              Remove Lighting and Mechanical Drop to Floor By Respective Trades  16  HRS  $120.00       $1,920
       46            Studio Connector
       47              Remove Portion of Roof/Roof Eve from Existing Building to tie new roof in  532  SF  $5.41  $2,880
       48              Remove 8 Exterior Doors                                     8   EA        $160.00         $1,280
       49              Remove Existing Exterior Siding                          1,002  SF          $3.84         $3,848
       50              Remove Rain Leaders and Boots                               5   EA        $100.00          $500
       51            Gymnasium
       52              Remove Gym Floor                                                                     In Abatement
       53              Remove all inserts and embedded items                       1   LS        $500.00          $500
       54              Shot blast adhesive                                      3,668  SF          $3.50        $12,838
       55              Perform moisture test                                       1   LS       $2,500.00        $2,500
       56              Remove Bleachers                                            1   LS       $3,000.00        $3,000
       57              Remove Trainers Rm,Stage, Offices - Building addition   36,476  CF          $1.00        $36,476
       58              Saw-cut wall for new doors                                  1   LS        $960.00          $960
       59              Remove Lighting and Mechanical Drop to Floor By Respective Trades  1  LS  $3,840.00       $3,840