3E. GENERAL CONDITIONS COSTS









                                                            Mercy  College
                                                Victory Hall Additions and Renovations           Date: July 27, 2017

           A/C   Description                            Qty.  Unit  Cost        Total                Remarks
                 Supervision:
                 On-Site Staff:
                      Principal in Charge  , Keith Stanisce  10  mos  $0               $0           No Charge
                      Project Manager, Greg Ondick       10   mos  $11,027         $110,270        24 hours / week
                      Project Superintendent,  Anthony Goodell  10  mos  $12,087   $120,870        40 hours / week
                      MEP Project Manager , Ron Cardillo  10  mos  $10,491         $104,910        16 hours / week
                      BIM Manager, Rob Goslin            10   mos  $3,725           $37,250        8 hours / week
                      Safety / Assist. Superintendent, Max Stanisce  10  mos  $9,621  $96,210      40 hours / week
                      Field Engineer/Plan Clerk, Gabe Martin   10  mos  $2,990      $29,900       12 hours / week
                 Support Staff:
                      Legal , Mike Mulqueen              10   mos    $0                $0           No Charge
                      Project Accounting , Awila Ocasio  10   mos  $1,123           $11,230        4 hours / week
                      Executive Assistant , Rosemarie D'Elia  10  mos  $2,370       $23,700        8 hours / week
                      IT Support , Jorge Murillo         7    mos  $1,161            $8,127        4 hours / week
                                             Supervisions:                         $542,467


                 Equipment and  General  Field Expense:
                    Scheduler                            5    mos  $1,200            $6,000
                    Smart Board                          1   allow  $3,500           $3,500
                    Building Design Suite Subscription   1    yr   $1,800            $1,800
                    GoTo Meeting Service                 1    yr    $500              $500
                    Field Office Equip. & Supplies       10   mos   $450             $4,500
                    Computers / Web Based System         3   allow  $2,200           $6,600
                    Telephone/Fax/Radios/Computers/Cell  10   mos   $650             $6,500
                    Postage, Messengers, Fed-Ex, etc.    10   mos   $140             $1,400
                    Field Office / Trailer               10   mos   $980             $9,800
                    Travel                               1   allow  $9,500           $9,500
                    Progress/Existing Conditions Photos  10   mos   $250             $2,500
                    Misc. General Expense                10   mos   $450             $4,500
                      Equipment and  General  Field Expense                         $57,100

                  Total General Conditions:                                        $599,567