3E. GENERAL CONDITIONS COSTS
Mercy College
Victory Hall Additions and Renovations Date: July 27, 2017
A/C Description Qty. Unit Cost Total Remarks
Supervision:
On-Site Staff:
Principal in Charge , Keith Stanisce 10 mos $0 $0 No Charge
Project Manager, Greg Ondick 10 mos $11,027 $110,270 24 hours / week
Project Superintendent, Anthony Goodell 10 mos $12,087 $120,870 40 hours / week
MEP Project Manager , Ron Cardillo 10 mos $10,491 $104,910 16 hours / week
BIM Manager, Rob Goslin 10 mos $3,725 $37,250 8 hours / week
Safety / Assist. Superintendent, Max Stanisce 10 mos $9,621 $96,210 40 hours / week
Field Engineer/Plan Clerk, Gabe Martin 10 mos $2,990 $29,900 12 hours / week
Support Staff:
Legal , Mike Mulqueen 10 mos $0 $0 No Charge
Project Accounting , Awila Ocasio 10 mos $1,123 $11,230 4 hours / week
Executive Assistant , Rosemarie D'Elia 10 mos $2,370 $23,700 8 hours / week
IT Support , Jorge Murillo 7 mos $1,161 $8,127 4 hours / week
Supervisions: $542,467
Equipment and General Field Expense:
Scheduler 5 mos $1,200 $6,000
Smart Board 1 allow $3,500 $3,500
Building Design Suite Subscription 1 yr $1,800 $1,800
GoTo Meeting Service 1 yr $500 $500
Field Office Equip. & Supplies 10 mos $450 $4,500
Computers / Web Based System 3 allow $2,200 $6,600
Telephone/Fax/Radios/Computers/Cell 10 mos $650 $6,500
Postage, Messengers, Fed-Ex, etc. 10 mos $140 $1,400
Field Office / Trailer 10 mos $980 $9,800
Travel 1 allow $9,500 $9,500
Progress/Existing Conditions Photos 10 mos $250 $2,500
Misc. General Expense 10 mos $450 $4,500
Equipment and General Field Expense $57,100
Total General Conditions: $599,567