3C. COST BREAKDOWN
Mercy College: Victory Hall RFP Response Pricing Matrix
Preconstruction Fee
STAFF FEE
Assumed 1 Month Total Duration STAFF FEE
85% Construction Documents
Exec/Admin Est/BIM Ops MEP
Meetings/Reviews/Administration 52 8 24 16 4 Hrs
Scheduling/Logistics/Safety/Mitigation 40 4 20 8 8 Hrs
Estimate/Control/Reconciliation 122 12 40 54 16 Hrs
BIM/Constructability/LEED/Bid Analysis 36 4 8 16 8 Hrs
Value Engineering/Option Studies 30 8 10 8 4 Hrs
Total Hours 280 36 110 112 40 Hrs $23,865
Staff Fee Total $23,865
REIMBURSABLES FEE
REIMBURSABLES FEE
Reimbursables Categories
1 Month Expenditure Quantity Unit Rate Total
Mail/Courier Expenses 1 MO $160 $160
Copy/Reprographic Expenses 1 MO $500 $500
IT/Communication Expenses 1 MO $100 $100
Travel/Lodging Expenses 1 MO $500 $500 $1,260
Reimbursables Fee Total $1,260
Note: Does not include the cost of invasive exploratory work and/or mock-up's
PRECONSTRUCTION FEES TOTAL $25,125
PRECONSTRUCTION FEE DISCOUNT -$12,625